Fukushima Dai-ichi nuclear plant: Reactor #3 control room powered up and cooling pumps to be switched on tomorrow

Progress at the Fukushima Dai-ihi nuclear plant continues steadily but slowly.External power is now available to all 6 reactors. Highlights today:

  • A high-powered water cannon truck has arrived from Australia at a US base in Tokyo to help recovery efforts at the Fukushima Daiichi nuclear power plant. The water cannon can shoot 150 liters of water per second at a target 150 meters away. It can also operate unmanned for 2 to 3 days while pumping seawater. It will be sent o Fukushima if needed.
  • A vehicle with a long spraying arm injected water into the No.4 reactor at the troubled Fukushima Daiichi nuclear power plant for about 3 hours on Tuesday. The vehicle, owned by a construction firm in Mie Prefecture in central Japan, began the operation at 5:17 PM Tuesday at the request of the Tokyo Electric Power Company. The vehicle is used in construction of high-rise buildings, and is capable of extending its arm more than 50 meters to pour concrete. The operation ended at about 8:30 PM.

Water spraying into Reactor #4: image nhk

  • Tokyo fire department started operation of spraying water to Unit-3 through cooperation with Osaka fire department. Water spraying  was conducted for one hour and finished around 16:00. Total amount of water sprayed is more than 3 times the pool capacity.
  • TEPCO said on Tuesday that it will restore power to the control rooms of No.3 and No.4 reactors as soon as water-spraying operations are completed to cool down fuel storage pools.
  • Defense Minister Kitazawa announced  that surface temperature measurement by helicopter will be conducted everyday, weather permitting, and not just twice a week in view of the smoke and steam that has been observed.

NHK World:

TEPCO has restored the electricity supply to the control room of the Number 3 reactor at the quake-damaged Fukushima Daiichi nuclear plant. Lights in the control room were switched on again on Tuesday night.
Eleven days have passed since the massive earthquake devastated northeastern Japan and cut off external power to the Fukushima Daiichi nuclear plant.
TEPCO reconnected power cables to the Number 3 and Number 4 reactors earlier on Tuesday.
TEPCO will now try to reactivate vital monitoring systems in the control rooms, such as those for measuring temperatures inside the reactors and water levels in the spent fuel storage pools. TEPCO says it will transmit electricity to the cooling pump for the Number 3 reactor on Wednesday. The company says if the pump functions normally, it will begin cooling the reactor and the spent fuel storage pool