Archive for March, 2011

TEPCO President goes AWOL – not seen in public since March 13th

March 27, 2011

While the toll of casualties keeps increasing it has emerged that TEPCO’s President Masataka Shimizu has gone into seclusion and has not been seen publicly since 13th March. In the meantime the leaderless TEPCO has retracted the very high radiation results from reactor #2.

The National police Agency’s figures for casualties from the earthquake and tsunami, as of Sunday night, exceeds 27,000 killed or missing:

Number of people killed 10,804

Number of people missing 16,244

At the Fukushima plant TEPCO has retracted the measurements of high radioactivity they announced earlier and give the impression, not so much of being clueless, but certainly of being without any coherent leadership.

NHK reports:

Tokyo Electric Power Company has retracted its announcement that 10 million times the normal density of radioactive materials had been detected in water at the Number 2 reactor of the Fukushima Daiichi nuclear plant.

The utility says it will conduct another test of the leaked water at the reactor’s turbine building.

The company said on Sunday evening that the data for iodine-134 announced earlier in the day was actually for another substance that has a longer half-life.

The plant operator said earlier on Sunday that 2.9 billion becquerels per cubic centimeter had been detected in the leaked water.

It said although the initial figure was wrong, the water still has a high level of radioactivity of 1,000 millisieverts per hour.

The perception of TEPCO being without leadership first built up when the President Masataka Shimizu tried to abdicate all responsibility for the site on March 14th and was severely told off by the Prime Minister and the government.

But it now emerges from Kyodo News that he has not been seen publicly since 13th March. He seems to have gone AWOL:

Masataka Shimizu, president of Tokyo Electric Power Co., which operates the crisis-hit Fukushima nuclear plant, fell sick March 16 and took some days off from the liaison office between the government and the utility firm, TEPCO officials said Sunday.

While Shimizu was away from the office set up at the firm’s headquarters, he collected information and issued instructions from a different room of the headquarters building to address the troubles at the Fukushima Daiichi nuclear power station hit by the March 11 quake and subsequent tsunami, the officials said. He has already recovered and come back to work at the liaison office, they said.

A TEPCO spokesperson declined to elaborate on his health condition, but said he did not fall over or need to be hooked up to an intravenous drip.

Shimizu has not appeared in public since attending a press conference on March 13, two days after the catastrophe that wreaked havoc on northeastern and eastern Japan.

Blood and oil in the sand: Is Gaddafi still getting the money from Libyan oil?

March 27, 2011

Apparently Libyan oil is still flowing while bombs are falling .

But who is getting the money for the oil?

And is oil the only reason why the West and Nato are supporting the rebels in Libya but not those opposing the oppresive regime in Bahrain?

Der Spiegel:

Are countries involved in the international operation in Libya hypocritical? That, it would seem, is the belief of German Development Minister Dirk Niebel, who criticized participants for continuing to draw oil from Libya. The comments show just how wide the gap between Berlin and its NATO allies has become. …

On Thursday evening,  Dirk Niebel  a member of Merkel’s junior coalition partners, the Free Democrats (FDP), accused the United Nations-backed military alliance currently operating in Libya of hypocrisy. 

“It is notable that exactly those countries which are blithely dropping bombs in Libya are still drawing oil from Libya,” he said.

Niebel also said that Germany was “not consulted” by France prior to the start of the campaign in Libya and added that European Union foreign affairs chief Catherine Ashton’s coordination of the EU position on Libya had been “suboptimal.”

Niebel’s comments came on the heels of a demand by Merkel, made during the ongoing European Union summit in Brussels, for a complete oil embargo against Libya. The international community, she said, “must clearly show that we will not do business with anyone who wages war against his own people.” …..

And the implied accusation that oil interests are one motivation behind the Libya mission is not likely to be well received in Western capitals. …

Meanwhile, on Thursday, an agreement was reached among NATO member states that the trans-Atlantic alliance would take control of the no-fly zone over Libya.

Towns, tribes and oil fields of Libya.

Fukushima Dai-ichi: Reactor No.2 suppression pool leaking highly radioactive water

March 27, 2011

BREAKING!

Very high levels of radiation have been measured in water leaking from reactor #2. It is thought that the breach is in the suppression pool.

TEPCO, says it has measured radiation levels of 2.9 GBq/cc in water from the basement of the turbine building attached to the Number 2 reactor. The level of contamination is about 1,000 times that of the leaked water already found in the basements of the Number 1 and 3 reactor turbine buildings. The measurements indicated 2.9 GBq/cc iodine-134, 13 MBq/cc of iodine-131, and 2.3 MBq /cc for each of cesium 134 and 137. This is clear evidence that fission is continuing.

University of Tokyo graduate school professor Naoto Sekimura says the leak may come from the suppression chamber of the Number 2 reactor, which is known to be damaged. The chamber is designed to contain overflows of radioactive substances from the reactor.

All workers have been evacuated from the reactor #2 building.

Fukushima Dai-ichi nuclear plant: Reactor vessel integrity may be compromised

March 26, 2011

Leakage of water with high levels of radioactivity  raise the possibility that there may be cracks in the reactor containment vessels of Reactors #1,2 and 3.  One saving grace is that the pressure in the vessels remains high and would argue against a breach. However cracks below the water level that permit some water seepage  cannot be ruled out. It is also possible that the leakage of radioactive water is not from the vessel itself but from some of the surrounding valves or piping.

The Guardian:

A suspected break in the core of a nuclear reactor could have been responsible for a leak of large amounts of radioactive contamination at the Fukushima Daiichi power plant, Japanese nuclear safety officials said on Friday, in another setback to efforts to avert disaster at the stricken facility.

In the latest developments, officials have said seawater outside one of the units has registered 1,250 the normal level of radiation, while efforts are under way to pump radioactive water that has pooled around the reactor turbines into safe storage. The BBC has reported that short-term radioactive iodine has been detected at very high levels in the Pacific Ocean near the plant.

US naval barges have started rushing in supplies of fresh water amid concerns the seawater being used to cool down the reactors might be causing corrosion. …

On Thursday three workers were exposed to unusually high levels of radiation after stepping in contaminated water in the turbine building of the crippled No. 3 reactor, which they were trying to cool.

Two received possible beta ray burns to their legs. All three have been transferred to a special radiation treatment facility. Kyodo news reported that the two more seriously injured workers could have suffered internal radiation exposure.

“The contaminated water had 10,000 times the amount of radiation as would be found in water circulating from a normally operating reactor,” said Hidehiko Nishiyama, a spokesman for Japan’s nuclear safety agency.

Nishiyama said it was unlikely that the reactor had cracked, but conceded that the unusually high levels of radiation appeared to have originated from its core. “It is possible there may be damage somewhere in the reactor,” he said, adding that a leak in the plumbing or the vents could also be to blame.

GE BWR cutaway : image inside.mines.edu

NHK World reports:

A high level of radioactive iodine has been detected in seawater near Japan’s troubled Fukushima Daiichi nuclear power plant. The facility was hit by the March 11th earthquake and tsunami.

The Nuclear and Industrial Safety Agency said on Saturday that iodine 131 in excess of 1,250 times regulated standards was found in seawater collected 330 meters south of a plant water outlet at 8:30 AM on Friday.

The agency says there is no immediate threat to people within the 20-kilometer evacuation zone. The agency adds that as seawater is dispersed by ocean currents the contamination level will decline.

Iodine 131 at146.9 times regulated standards was detected in seawater in the area on Wednesday.

Saturday, March 26, 2011 12:44 +0900 (JST)

Kyodo News:

TEPCO, is currently injecting fresh water into the No. 2 reactor core to prevent crystallized salt from seawater already injected from forming a crust on the fuel rods and hampering the smooth circulation of water, thus diminishing the cooling effect. It has begun injecting fresh water into the No. 1 and No. 3 reactor cores.

At the same time, the firm is trying to remove pools of water containing highly concentrated radioactive substances that may have seeped from either the reactor cores or the spent fuel pools, while also trying to restore power at the No. 2 reactor.

On Thursday, three workers were exposed to water containing radioactive materials 10,000 times the normal level at the turbine building connected to the No. 3 reactor building. On Friday, a pool of water with similarly highly concentrated radioactive materials was found in the No. 1 reactor’s turbine building, causing some restoration work to be suspended.

Similar pools of water were also found in the turbine buildings of the No. 2 and No. 4 reactors, measuring up to 1 meter and 80 centimeters deep, respectively. Those near the No. 1 and No. 3 reactors were up to 40 cm and 1.5 meters deep. ..

The U.S. Department of Energy said in its radiological assessment released Friday that by comparing aerial measurement data from Thursday with previous measurements, the data indicate peak exposure rates in the western side of the Fukushima plant are lower.

 

Radioactive water leaks from 3 reactors – fresh water cooling started

March 25, 2011

The path to complete cooling and stability will not be smooth or easy at Fukushima Dai-ichi nuclear plant. New complications and setbacks in Reactors #1,2 and 3 are leading to new strategies and actions. There will no doubt be many more such challenges in the days and weeks ahead.

Update 25th March midnight JST (1600 CET):

TEPCO said Friday it has begun injecting freshwater into the No. 1 and No. 3 reactor cores at the crisis-hit Fukushima Daiichi nuclear plant to enhance cooling efficiency, although highly radioactive water was found leaking possibly from both reactors as well as the No. 2 reactor.

The latest efforts to bring the troubled reactors at the plant under control are aimed at preventing crystallized salt from seawater already injected from forming a crust on the fuel rods and hampering smooth water circulation, thus diminishing the cooling effect, the plant’s operator said.

A day after three workers were exposed to water containing radioactive materials 10,000 times the normal level at the turbine building connected to the No. 3 reactor building, highly radioactive water was also found in the turbine buildings of the No. 1 and No. 2 reactors.

Early Friday, concern grew that the high-level radiation leak detected with the workers’ exposure Thursday could indicate possible damage to the No. 3 reactor vessel, but the government’s nuclear safety agency later denied the possibility, saying no data, such as on the pressure level, have suggested the reactor vessel has cracked or been damaged. The No. 3 reactor used plutonium-uranium mixed oxide fuel for so-called ”pluthermal” power generation.

While the high-level radiation is suspected to have come from the reactor, where overheating fuel rods are believed to have partially melted, it remains uncertain how the leak occurred, said Hidehiko Nishiyama, spokesman for the government’s Nuclear and Industrial Safety Agency.

He said further verification is needed to find out how the radioactive water reached the underground site where the workers were exposed. Huge volumes of water have been poured into the reactor as well as its apparently boiling spent fuel pool since they lost their cooling functions.

In addition to the infusion of freshwater to the No. 1 and No. 3 reactors, it injected seawater to the spent fuel pools of the No. 2 and No. 4 reactors through pipes, and firefighters sprayed a massive amount of seawater onto the No. 3 fuel pool, the utility said.

The government, meanwhile, encouraged residents within 20 to 30 kilometers of the plant to leave voluntarily, citing concerns over access to daily necessities, while maintaining its directives for them to remain indoors and for residents within 20 km of the plant to evacuate.

Fukushima Dai-ichi nuclear plant: Status on March 25th

March 25, 2011

It is 2 weeks today since the quake and Tsunami struck. The toll of dead and missing exceeds 27,000.

Progress continues steadily but painfully slowly at the Fukushima Dai-ichi nuclear plant. The radiation levels are fluctuating but pose no health hazard to the general public. Containment vessel at Reactor #3 is damaged and may be causing radiation spikes.

From JAIF

  • The work to restore external AC power for units-1, 2, 3 and 4 is in progress. External AC power to the main control room at unit-2 will be available today. According to TEPCO, the reactor surface temperature at unit-1 increased to  approx. 400 ° C once (design assumption maximum 302 ° C).  Now it has dropped to 204.5 ° C (as of 06:00 on March 25).
  • Meanwhile,  in the turbine building at unit-3, drainage work is also in progress. (10:45, March 25)
  • On March 24, 2 workers, who were working to lay electrical cables in turbine building at unit-3, were sent to the hospital. TEPCO suspected that the nuclear fuel in the reactor or spent nuclear fuel at the pool was damaged and water contaminated with high radioactivity was leaked  to the workspace. Further investigation is now carrying on. These 2 workers were not wearing boots. Another worker wearing boots is safe. (07:15, March 25).
  • As for the coolant of reactors at Fukushima Daiichi, TEPCO would like to switch from seawater to fresh water as fast as possible. The first switch will be carried out at unit 3. (04:30, March 25)
  • Ministry of Defense announced that the Self-Defense Force helicopter measured the surface temperatures of Fukushima Daiichi units-1, 2, 3 and 4 from the air by using infrared rays and  found that the temperature of each units is below 20 ° C. Unit-1:17 ° C; Unit-2: 13°C; Unit-3: 11 °C; Unit-4: 17 °C (as of the morning on March 24). Especially, the surface temperature of the spent fuel pool at unit-3 dropped significantly to 31 °C, compared to 56°C on the previous day. (21:15, March 24)

From IAEA:

Unit 1: Workers have advanced the restoration of off-site electricity and lighting in the Unit’s main control room was recovered as of 24 March, 11:30 UTC. They are now checking the availability of the cooling system. While the pressure in the reactor vessel remains high, Japanese authorities are reporting that it has stabilized.

Unit 2: Engineers are working for the recovery of lighting in the main control room, and the instrumentation and cooling systems.

Unit 3: Around 120 tonnes of seawater was injected in the spent fuel pool via the cooling and purification line. The operation was carried out between 23 March, 20:35 UTC and 24 March, 07:05 UTC. Work was under way for the recovery of the instruments and cooling systems. However, it had to be suspended because three workers were exposed to elevated levels of radiation on 24 March.

Unit 4: The spent fuel pool was sprayed with around 150 tonnes of water using concrete pump truck. The operation was carried out between 24 March, 05:36 UTC and 06:30 UTC of the same day.

Units 5 and 6: Repair of the temporary pump for Residual Heat Removal (RHR) was completed as of 24 March, 07:14 UTC, and cooling started again 21 minutes later.

At the Common Spent Fuel, the power supply was restored as of 24 March, 06:37 UTC and cooling started again 28 minutes later. Work is now under way for the recovery of the lighting and instrumentation systems. As of 24 March, 09:40 UTC, the water temperature of the pool was around 73 °C.

As of 24 March, 10:30 UTC workers continue to inject seawater into the reactor pressure vessels of Units 1, 2 and 3 and are preparing to inject pure water.

 

Gaddafi & family activate Plan B to save themselves

March 25, 2011

That Gaddafi and family are not the kind to die heroically fighting to the last breath for some matter of principle is fairly clear. That their private aircraft were flitting around the world a few weeks ago secretly shifting and hiding their assets is an educated presumption. It seems increasingly likely that a “Plan B” for survival anda re-grouping is being put into effect as the “no-fly zone” and sanctions and the world-wide freezing of Libyan assets takes effect.

Belarus – not Venezuela – maybe Gaddafi’s bolt-hole

Map indicating location of Belarus and Libya

Belarus and Libya: image Wikipedia

My reading is that the family have already prepared their bolt hole most probably in Belarus and that Venezuela and Cuba are not viable. Kazakhstan and Tajikistan are remotely possible. I would not be surprised if the sudden flight of his nurse Galyna Kolotnytska back to Ukraine at the end of February was executed as part of Plan B. But the problem for Gaddafi and his family is now to arrange a “safe passage” to wherever the bolt-hole has been prepared.

Reuters reports:

Members of Muammar Gaddafi’s entourage are putting out feelers to seek a ceasefire or safe passage from Libya.

Roger Tamraz, a Middle Eastern businessman with long experience conducting deals with the Libyan regime said Saif al-Islam Gaddafi, Muammar’s eldest son, and Abdullah Senoussi, the Libyan leader’s brother-in-law, were the most prominent Gaddafi entourage members involved in seeking ways to end the fighting. A U.S. national security official, who asked for anonymity when discussing sensitive information, said that U.S. government agencies were aware that Saif al-Islam and Senoussi had been involved in making peace overtures.

“It’s clear that some of Gaddafi’s family members always have a plan B up their sleeve. That doesn’t mean they’ll leave and certain Gaddafis are probably going to stick with their crazy dad no matter what happens,” the U.S. official said.

In an interview on Tuesday with a U.S. television network, Secretary of State Hillary Clinton said she was aware that people close to Gaddafi had been trying to make contact.

“I’m not aware that he personally has reached out, but I do know that people allegedly on his behalf have been reaching out,” Clinton told ABC America’s Diane Sawyer.

“This is what we hear from so many sources…Today, yesterday, the day before. Some of it…is theater, some of it is kind of, shall we say, game-playing…But some of it, we think, is exploring, ‘what are my options, where could I go, what could I do.’ And we would encourage that,” Clinton said.

The U.S. national security official added: “It’s not at all surprising that members of the Gaddafi regime might be looking for ways out of this mess.” …..

Tamraz told Reuters that some of the most aggressive efforts by members of Gaddafi’s entourage to start dialogue were being channeled through Austria. A European government financial investigator said that Libya was believed to have extensive wealth and investments in Austria.

Tamraz said that he believed Saif al-Islam, Senoussi and other members of the Gaddafi entourage were proposing a ceasefire between government forces, rebels and the anti-Gaddafi Western alliance, or plans which would enable members of the Libyan leader’s entourage to go into exile peacefully.


Two 7.0 quakes hit Burma — as predicted?

March 24, 2011

Update 25th March! Reports are now beginning to come in of over 50 70 killed.

In the light of  the recent predictions of increased earthquake activity especially in the period 22nd – 27th March, two large 7.0 quakes – as if on cue – have rocked north east Burma (Myanmar) close to the borders with Laos and Thailand.

The prediction was made by Jim Berkland and Piers Corbyn and points to solar effects as the trigger.

The are hit by the two quakes are remote  and even if large numbers of people and heavy infrastructure are not involved,  at magnitude 7.0 they are very powerful quakes and they may have been devastating for the people in this very poor region. One of the quakes was very shallow and may have caused much destruction.

One more major quake in the Pacific Rim region in the next 3 to 4 days will, I think, be a very strong indicator that we should be looking mainly at the sun in efforts to anticipate what triggers earthquakes. Tectonic plate movement clearly describes the build up of forces in the earth’s crust but what triggers particular quakes at particular times is largely unknown.

BBC reports:

map

Burma earthquake 24th March 2011

North-east Burma has been rocked by two 7.0 magnitude earthquakes, close to the borders with Laos and Thailand, the US Geological Survey has reported.

They struck seconds apart at 1355 GMT and were centred about 70 miles (110 km) from the northern Thai city of Chiang Rai, the agency said.

The first quake was shallow, at a depth of 6.2 miles (10km), while the second was much deeper at 142.5 miles (230km).

Tremors could be felt as far away as Bangkok and Hanoi. The area where the quakes struck is sparsely populated and remote. The BBC’s Rachel Harvey in Bangkok said it could be a while before the extent of the damage is known.

Seismic monitor

article image

chart from iris.edu

ABOVE chart from iris.edu

WordPress blogging hiccups

March 24, 2011

For the last 24 hours I have been having difficulties and saving and publishing posts has been a little haphazard.

Presumably this is because of the massive attacks WordPress.com has been subjected to though it is not clear to me why such attacks would be motivated.

After having lost a couple of posts I shall take a day or two off  from blogging and hope that the hard-pressed staff of WordPress succeed in their efforts to stave off the attacks and make their sites even more robust.

Fukushima Dai-ichi nuclear plant: Reactor #3 control room powered up and cooling pumps to be switched on tomorrow

March 23, 2011

Progress at the Fukushima Dai-ihi nuclear plant continues steadily but slowly.External power is now available to all 6 reactors. Highlights today:

  • A high-powered water cannon truck has arrived from Australia at a US base in Tokyo to help recovery efforts at the Fukushima Daiichi nuclear power plant. The water cannon can shoot 150 liters of water per second at a target 150 meters away. It can also operate unmanned for 2 to 3 days while pumping seawater. It will be sent o Fukushima if needed.
  • A vehicle with a long spraying arm injected water into the No.4 reactor at the troubled Fukushima Daiichi nuclear power plant for about 3 hours on Tuesday. The vehicle, owned by a construction firm in Mie Prefecture in central Japan, began the operation at 5:17 PM Tuesday at the request of the Tokyo Electric Power Company. The vehicle is used in construction of high-rise buildings, and is capable of extending its arm more than 50 meters to pour concrete. The operation ended at about 8:30 PM.

Water spraying into Reactor #4: image nhk

  • Tokyo fire department started operation of spraying water to Unit-3 through cooperation with Osaka fire department. Water spraying  was conducted for one hour and finished around 16:00. Total amount of water sprayed is more than 3 times the pool capacity.
  • TEPCO said on Tuesday that it will restore power to the control rooms of No.3 and No.4 reactors as soon as water-spraying operations are completed to cool down fuel storage pools.
  • Defense Minister Kitazawa announced  that surface temperature measurement by helicopter will be conducted everyday, weather permitting, and not just twice a week in view of the smoke and steam that has been observed.

NHK World:

TEPCO has restored the electricity supply to the control room of the Number 3 reactor at the quake-damaged Fukushima Daiichi nuclear plant. Lights in the control room were switched on again on Tuesday night.
Eleven days have passed since the massive earthquake devastated northeastern Japan and cut off external power to the Fukushima Daiichi nuclear plant.
TEPCO reconnected power cables to the Number 3 and Number 4 reactors earlier on Tuesday.
TEPCO will now try to reactivate vital monitoring systems in the control rooms, such as those for measuring temperatures inside the reactors and water levels in the spent fuel storage pools. TEPCO says it will transmit electricity to the cooling pump for the Number 3 reactor on Wednesday. The company says if the pump functions normally, it will begin cooling the reactor and the spent fuel storage pool